Incident Report: 20131201: Difference between revisions
No edit summary |
No edit summary |
||
| Line 3: | Line 3: | ||
{{Incident | {{Incident | ||
|brief=A displeased 12kV power cable shorted, taking out parts of the local power grid. URY's servers were unhappy with this series of events, so massaging was needed. | |brief=A displeased 12kV power cable shorted, taking out parts of the local power grid. URY's servers were unhappy with this series of events, so massaging was needed. | ||
|severity= | |severity=Critical | ||
|impact= | |impact=Medium (main outage at night, residual issues were for minor services) | ||
|start=01/12/2013 01:42 | |start=01/12/2013 01:42 | ||
|end=01/12/2013 07:11 | |end=01/12/2013 07:11 | ||